8/14 Beijing-Shenyang Passenger Dedicated Railway Line Hebei Section Lot 2 (Chengde)

PEC + S Ltd.. Beijing with PEC + S GmbH, Munich, a holding company of Gauff Rail Engineering and SSF Ingenieure AG, gets together with the Chinese partner Construction  Consulting and Supervision Co., Ltd.. (Wuhan) of CRFSDI the contract for supervision activities for the construction of the new high-speed Beijing-Shenyang Passenger Dedicated Railway Line / Hebei Section / Lot 2 (Chengde).

 

Client:Beijing-Shenyang and Beijing-Hebei PDL Co.,Ltd., No. 16 Laocanju alley, Dongcheng District, Beijing, China
Design speed:vD = 350 km/h – ballastless track; operation speed 300 km/h
Length:54.7 km
Subgrade:14.4 km
Bridges:16.8 km
Tunnels:22.8 km
Stations:2 (Pingquan North, North Chengde Station)
Girder fabrication yards:3 (493 girder)
Large bridges:4 cantilever bridges
Service period:2014 – 2019
Construction period tunnel:01.10.2014 – 31.08.2017 (longest tunnel)
Constructions period bridges:approx. 26 months
Services:Consulting and Site Supervision for earthworks, cuts and embankments, engineering structures, tunnels and bridges; production of prefabricated single-span girders with 32 and 24 m span; Supervision of cast-in-situ girder construction on site.

News

8.03.2017

While the works at Henan section of the 818 km long High Speed railway line from Zhengzhou, the...

19.08.2016

The expansion of the high-speed rail network is an important objective in China, a country where...

17.12.2015

Messrs Huo Yi and Zhu Gui Fu, chefs of the Chinese engineering office Beijing, assessed the quality...